The Iraqi Megaproject No One Thought Would Happen Is Racing To Completion

Key elements of TotalEnergies’ four-pronged $27 billion project that will define Iraq’s oil and gas industry for years to come are 80 to 95 percent complete, according to a report from Iraq’s oil ministry. Rehabilitation work on the first central processing facility (expected to increase capacity from 60,000 barrels per day to 120,000 barrels per day) is 80% complete, while the Artawi-PS1 export pipeline project is 95% complete. Overall, a senior source working closely with the ministry exclusively revealed Oil Price Network Weekend: “It [TotalEnergies] is doing what it promised, ahead of schedule on multiple fronts, because it has been allowed to proceed with these projects with little to no usual government interference. He added: “If the rest of the work continues as it is, then we will be on track to achieve a huge increase in oil production in a relatively short period of time.” “

Indeed, the Common Seawater Supply Project (CSSP), a key element of TotalEnergies’ four-part plan, has long promised that Iraq would eventually be able to realize its full hydrocarbon potential and become one of the world’s top three oil producers – perhaps second only to the United States. As I fully analyze in my latest book on the new order in the global oil market, CSSP involves obtaining and treating seawater from the Persian Gulf and then transporting it via pipelines to oil production facilities to maintain reservoir pressure. This will optimize field life and production. The basic plan for the CSSP is that it will initially be used to supply about 6 million barrels per day of water to at least five oil fields south of Basra and one oil field in Maysan Province, and then expanded to other oil fields. Iraq’s long-important Kirkuk and Rumaila fields (the former began production in the 1920s and the latter in the 1950s, and both account for about 80% of the country’s cumulative oil production) require large and sustained water injections. The former’s reservoir pressure dropped significantly after producing only about 5% of its oil in place (OIP), while Rumaila produced more than 25% of its oil in place before requiring water injection, according to the International Energy Agency (IEA). This is because Rumaila’s main reservoir is connected to a very large natural aquifer, which helps push oil out of the reservoir.

See also  Ireland defeat reminiscent of end of my era - Jones

According to the IEA, in order to meet and maintain Iraq’s future crude oil production targets over any meaningful period, Iraq’s total water injection needs will be equivalent to about 2% of the average combined flow of the Tigris and Euphrates rivers, or 6% of the total flow during the off-season. While these levels of water withdrawal appear manageable, these water sources must also continue to meet the requirements of other end-use sectors, including the large agricultural sector. Saudi Aramco’s Qurayyah seawater plant expansion project provides a wealth of information on potential timelines for completion of the CSSP. The 2 million barrels per day expansion of the existing facility took nearly four years, from the award of the front-end engineering, procurement and design contract in May 2005 to the first start of water connections in early 2009.

Spread the love

Leave a Reply

Your email address will not be published. Required fields are marked *